PMMI ProSource – Start Your Search
Check out our packaging and processing solutions finder, PMMI ProSource.

COVID-19 Test Medium Production Ramped Up By 20,000% in Six Months

Viral Transport Media tubes filled with liquid media are used to store and transport nasal swabs for viruses including COVID-19. Sixteen integrated lines were designed, built and installed in 20 weeks to meet demand.

VTM tubes filled with liquid medium are used to store and transport nasal swabs for viruses including SARS-CoV-2.
VTM tubes filled with liquid medium are used to store and transport nasal swabs for viruses including SARS-CoV-2.

“Nimble” is an understatement for most life science manufacturers producing COVID-19 test materials, PPE, or treatment this year.

Thermo Fisher Scientific snapped into action and began ramping up production of its viral transport media (VTM) tubes at the outset of the pandemic. Later they received orders from the U.S. government to scale production from 50,000 per week to 10 million per week. 

VTM tubes filled with liquid medium are used to store and transport nasal swabs for viruses including SARS-CoV-2. In March, the Thermo Fisher facility in Lenexa, KS, was already filling 10 and 15 mL conical tube configurations. The company ramped to 24/7 operation and retrofitted their lines to run faster at the outset of the pandemic, but it was clear that they needed new machines to meet demand. Considerations beyond speed included:

  • Some of the conical tubes are skirted, but the tubes without skirting do not stand up on their own.
  • The medium has similar viscosity to water, but Jason Gourley, strategic projects, sr. project engineer at Thermo Fisher Scientific, says, “From a filling perspective it's very similar to water, but if it lands on a surface, drips, or spills and begins to dry, it becomes sticky. If it's not immediately wiped or cleaned, it turns into a goo, similar to spilled soda left to dry.”

This didn’t cause issues with capping, but if a tube happened to spill and medium got on other components—such as the feed screws or labeler—equipment could bind up and cause downtime in cleaning. 

VTM lines also needed to be ramped up at Thermo Fisher’s sites in Perth, Scotland, and Wesel, Germany. In both Perth and Wesel, the operation switches between filling VTM and saline, depending on current demand. Gourley explains, “It's the same tube and cap, same fill size. The difference is the liquid itself, the labeling requirements, and different pump settings.”


See it Live at PACK EXPO Connects Nov. 9-13: Prevent E-commerce Package Leaks, by Selig Group. Preview the Showroom Here.


Speedy timeline

When Gourley arrived in Lenexa from his usual Rockford, IL facility in March, the immediate need was to understand the process and determine where automation could increase throughput dramatically.

Speed was key. The Thermo Fisher project team had vendors offering to drive components to the facility—instead of overnight or two-day shipping—because they knew every hour counted.

Gourley suggested working with Morrison Container Handling Solutions for high speed integrated lines. “I've worked with Morrison for about three or four years. They've done some screw feeds and integration with a line in Rockford.”

The initial request to Morrison was whether they could create a smaller system within approximately a week. “They immediately hopped on it and followed through. They had a quote ready the next day, working through the night and everything," he says. Some projects take a step-wise approach to implementation. But Gourley says time didn’t allow for that in this case, noting, “This was all at once. We drew it out on a napkin one morning. The next morning, we were putting it together.”

It was difficult to nail down project specifics with a constantly moving target. “Every day something changed. One million per week was the initial goal and it was only going to be for about three or four months,” Gourley says. “Everything started out with, ‘Maybe. But could you do it?’ We had four on order and then the question came down from the government on how we can get 10 million a week and what would it take.”

The original order for machine #1 was placed in early April and the first machine shipped in approximately five weeks. That included design from scratch to manufacturing, build/assembly, and testing. A total of 14 systems shipped to Lenexa and two systems shipped overseas in the next 20 weeks. To put things in perspective, the normal quoted lead time for one system/line can be 20 weeks or more.  

System details

The Morrison systems allow Thermo Fisher to orient, contain, move, and support the pointed conical tubes. They are handled from a dual feeder bowl solution to drop into the screws. (R-Tech Feeders Inc. based in Rockford, IL, supplied the tube elevators, feeder bowls, and shuttle dropping mechanism for the tubes into the Morrison screws.) The system then indexes six tubes at a time underneath the filling head, indexes along underneath the cap applicator, and then into a spindle capper. (APEX Filling Systems in Michigan City, IN, supplied the cap sorters and cappers.)